|

Newly laid track will be shown in Blue.
While we have been waiting for planning permission we have not
been idle and have removed the turf, laid "Terram" (a special geo-textile) and
laid ballast on top - there is still more ballast waiting to be applied
Letters on the pictures below refer to approximate locations on the
Paddock/Hanwoth Loop Plan above
(the track plan is only indicative)
Updated June 2010
|

A. John Morsen and Robert Leadbetter talking to the
‘locals’ as they erect the electric fence. |

B. The
‘Team’ installing the security box for the
battery to power
the electric fence. |
|
The electric fence in place and
functioning for several weeks and we started work on ‘digging’ the Hanworth
loop, on 26th April 2010, clearing the turf and topsoil.

C: Mich Hughes digs around the N.East
curve.
|
In three days the circuit was dug, the Terram laid and
sufficient ballast laid on top to keep the Geotextile
in
place
and (in places) enough to keep it from de-grading
in
the sun.

D. Douglas at the South
end of the Station Site.
May 2010
|
|